Go Back   2023 2024 MBA > MBA > Online MBA Discussions

  #1  
Old 16th November 2015, 03:50 PM
Unregistered
Guest
 
Default GTU MBA, 2nd Sem., Production and Operations Management Exam past Papers

Sir I want the Gujarat Technological University MBA, 2nd Sem., Production and Operations Management Exam past Papers so can you please give me the same
Reply With Quote Quick reply to this message
  #2  
Old 16th November 2015, 04:39 PM
Super Moderator
 
Join Date: May 2012
Default Re: GTU MBA, 2nd Sem., Production and Operations Management Exam past Papers

Here I am giving you the Gujarat Technological University MBA, 2nd Sem., Production and Operations Management Exam past Papers


Q.1 (a) Define operations management. Describe input-transformation-output
relationship in an automobile factory, a restaurant, and a super market.
07
(b) List the major reasons for and against locating a new apparel manufacturing
plant into a city.
07
Q.2 (a) Define costs associated with inventory.
Consider the data pertaining to purchase of a component as given below for a
small manufacturing organization:
Annual demand- 1200 units
Cost of ordering- Rs.15 per order
Cost of holding inventory- Rs.2.5per unit per year
Price- Rs. 25 per unit
Average working days in year- 365
Lead time- 7 days
Calculate (i) EOQ, (ii) reorder point, and (iii) total annual cost associated to
inventory.
07
(b) State the advantage of exponential smoothing method of forecasting.
Consider following data for a product having trends in demand given as under:
Initial exponentially smoothed forecast for period t- 120 units
Exponentially smoothed trend for period t- 12 units
Alpha- 0.2 and Delta- 0.28
If actual demand was observed to be 145 against the forecast of 120, calculate
(i) the forecast and (ii) trend for next period.
07
OR
(b) Explain the three strategies in aggregate planning. Distinguish between pure and
mixed strategies. What are the four major costs associated with these strategies?
07
Q.3 (a) “Project control should always focus on the critical path”- critically examine the
statement.
07
(b) Define sequencing. State ‘shortest processing time’ and ‘earliest due date’
priority sequencing rules.
For the data given as under, calculate (i) flow time, (ii) total flow time and (iii)
mean flow time using above sequencing rules.
Job
( as per arrival if the orders)
Processing Time
(days)
Due Dates
(day)
A 5 10
B 6 8
C 4 9
07
2
OR
Q.3 (a) The data for a project is collected as shown here under:
Activity Preceding activities Time (days) required Cost Rs.
Normal Crash Normal Crash
A - 6 4 13000 14000
B A 4 3 10000 11000
C A 5 3 11000 12000
D B 7 5 13000 16000
E B,C 2 2 8000 8000
F C 4 3 10000 13000
G E, F 5 4 14000 19000
H D, E 6 4 12000 17000
I H, G 8 5 18000 24000
(i) Draw the project network and show critical path. (ii) Calculate estimated
project completion time. (iii) To crash the project by three weeks, which activities
should be crashed and what shall be the cost of crashing?
07
(b) What do you understand by ‘shop floor control’? What are its functions? Explain
Gantt chart as a tool for shop floor control.
07
Q.4 (a) What is ‘line structure’ in waiting lines? Explain single channel- single phase,
multi channel- single phase and multi channel- multiphase line structures.
07
(b) Define supply chain management. Explain the recent changes in business
environment which made supply chain management highly important.
07
OR
Q.4 (a) With reference to supply chain strategy, explain the concept of ‘Bull Whip
Effect’. Compare the efficient supply chains v/s responsive supply chains.
07
(b) List the applications of waiting line management techniques. Consider following
data regarding a waiting line problem.
A university is considering opening a fee collection counter at university
canteen. The student’s arrival rate is estimated as 12 per hour. The estimated
average service time per student is 4 minutes. Assume arrival according to
Poison and service according to Exponential distribution. Calculate
Average utilization of counter clerk
Average number of students in waiting line
Average number of students in the waiting line system
Average time for which a student will wait in waiting line
Average waiting time in the system, including service time.
07
Q.5 (a) Discuss the contribution of Deming, Juran and Crosby in the field of quality. 07
(b) Explain the pull approach of JIT manufacturing. Compare it with conventional
push approach.
07
OR
Q.5 (a) Briefly explain the seven elements to achieve waste elimination in JIT. 07
(b) Draw the ‘operating characteristics’ curve and explain ‘producer’s risk’ and
‘consumer’s risk’.
Reply With Quote Quick reply to this message
Reply

Similar Threads
Thread Thread Starter Forum Replies Last Post
Past papers of vu MBA Saksham Online MBA Discussions 2 19th April 2018 07:56 AM
MBA Project Report on Production Management Download neetu Main Forum 2 5th April 2018 10:21 AM
Free Download MBA Project Report On Production Management payal Online MBA Discussions 2 27th March 2018 02:38 PM
MBA In Operations Management Details mamta Online MBA Discussions 2 24th March 2018 04:44 PM
NTS Past Papers for MBA payal Online MBA Discussions 2 19th February 2018 03:00 PM
AJKPSC Past Papers Unregistered Main Forum 1 3rd July 2017 02:36 PM
AH Maths Past Papers Unregistered Main Forum 1 8th December 2016 09:11 AM
SRMEEE Past Papers Unregistered Main Forum 1 24th November 2016 05:53 PM
MBA Operations Management IGNOU Unregistered Main Forum 1 10th November 2015 03:01 PM
MBA Operations Management UK Unregistered Main Forum 1 7th November 2015 04:10 PM
MBA Operations Management Chennai Unregistered Main Forum 1 7th November 2015 10:21 AM
University of Punjab Past Papers from BA Papers Unregistered Main Forum 0 16th July 2015 10:25 AM
MBA Part Time Second Semester Production Management Question Papers jugendra rana Main Forum 3 16th November 2014 09:56 PM
NTSE Stage II Exam Past Papers Unregistered Main Forum 1 13th October 2014 04:46 PM
Food Corporation of India (FCI) Exam Past Question Papers Unregistered Main Forum 1 8th October 2014 03:51 PM
Jobs for MBA Freshers In Operations Management Operations MBA Jobs vamshim Main Forum 1 23rd March 2013 10:54 AM
Quick Mba Operations Management suraj binnani Main Forum 1 18th March 2013 11:57 AM
MIT MBA Operations Management Ajinderjeet Singhji Main Forum 1 20th October 2012 05:49 PM
Surveying past Exam Papers prtik udai Main Forum 1 13th September 2012 10:12 AM
MFA production management milan Main Forum 1 16th July 2012 02:06 PM


Quick Reply
Your Username: Click here to log in

Message:
Options




All times are GMT +5.5. The time now is 09:01 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.
Search Engine Friendly URLs by vBSEO 3.6.0 PL2

1 2